I PHASE CONSTRUCTION WORKS STARTED

Construction works on the building with 106 apartments under the 1st Project phase started on 16 July 2018 and are conducted following the agreed timetable.

The deadline for the completion of works is 16 January 2020.

After the completion of preliminary and earthworks on 21 August 2018 a reinforced concrete counter-slab was poured.

 

1-Ispitivanje-nosivosti-tla

1) Assessment of the soil conditions

 

2-Siroki-iskop-I

2) Ground breaking – excavation

 

3-Ugradnja-tampon-sloja

3) Installing a layer of gravel

 

4-Izlivanje-KP

4) Counter-slab poured

 

5-Povezivanje-arm-KP

5) Installing rebar

 

6-Hor-Hi-KP

6) Hydro isolation is laid on the ground